Study Finds Ponta do Pargo Golf Course Unviable

Study Finds Ponta do Pargo Golf Course Unviable

Madeira's own feasibility study finds the Ponta do Pargo golf course financially unviable, as PS lawmakers question a lower tender price and a €60 million spend.

A feasibility study commissioned by Madeira's regional government concludes that the golf course under construction at Ponta do Pargo, in the Calheta municipality, is not financially viable as a public project. Opposition lawmakers from the Socialist Party (PS) revealed the finding this week.

The disclosure comes as construction on the course moves into an advanced stage, and as a public tender for the surrounding real estate land moves toward its deadline with a lower starting price than originally planned.

PS lawmakers said they found the price cut odd. They asked the government which studies and partners backed the decision. In response, they were sent the project's own feasibility study - and found that the study itself states the golf course, as a public investment, is not financially viable.

The study itself indicates that the golf course, as a public project, is financially unviable.

Goncalo Leite Pelho, PS , RTP Madeira

The regional government does not dispute the finding. It argues that no golf course anywhere in the world is financially self-sustaining on its own.

Such projects, officials say, always need to be paired with hotel or real estate investment, as is the case at Ponta do Pargo. A golf course cannot sustain itself on green-fee sales alone.

Ponta do Pargo golf course siteRelatedPonta do Pargo Golf Course: Detaching Policy from Local RealityMadeira spends €12 million to build its fourth golf course in a protected area, despite a widespread decline in purchasing power, an existential housing crisis and limited road infrastructure.

Tender Price For Golf Concession Falls to €16 Million

The public tender covers both the concession to run the golf course and the sale of land earmarked for real estate around it. Its base price was cut from 18 million euros to 16 million euros, payable in four installments, with a large discount against the concession's original value.

Ponta do Pargo golf project, key figures
Figure
Base price, concession and land sale16 million euros
Before: 18 million euros
Payment terms4 installments
Ponta do Oeste company investment to dateabout 60 million euros
Return from the direct concession alone18 million euros
Villas planned160
Hotels planned2
Estimated wealth from construction alone160 million euros
Golf course completionfirst half of 2027
Tender deadline20 November 2026

A separate, smaller error also affected the tender when it was launched. The original land valuation covered more land than is actually being sold, and the government says the tender has since been corrected to match the area that will actually change hands.

Public Developer Has Invested About €60 Million So Far

The golf course and its surrounding land belong to Ponta do Oeste, the public company that has developed the site. PS lawmakers say the company has invested about 60 million euros in the project so far, most of it on buying the land. That process began roughly 20 years ago and is ending this year as planned.

Against that spending, the direct concession alone is expected to bring back only 18 million euros. PS lawmakers call the resulting loss very large, comparing its scale to the cost of building a new marina at Lugar de Baixo.

Because the golf course is run as a concession rather than sold outright, the land itself stays with the public company. It keeps that underlying asset even if the concession and land sale underperform.

Plan Calls For Two Hotels Alongside New Villas

The wider project foresees 160 villas and two hotels built around the golf course. PS lawmakers say the feasibility study's main economic benefit actually comes from building those villas in Calheta, not from the golf course itself.

They argue that building villas in Calheta does not require public investment, since the area already has no shortage of housing for sale. The study also prices the villas' land below the current market value, the lawmakers say.

Construction Alone Seen Adding €160 Million in Wealth

Despite finding the golf course financially unviable on its own, the feasibility study rates the wider project as economically viable - highly viable, officials say - across three different scenarios. Much of that wider benefit comes from construction activity.

Officials estimate construction work alone, covering the golf course, the hotels and the real estate, will generate about 160 million euros in wealth. PS lawmakers argue the government will not recover anywhere close to what it has spent on the golf course itself, even counting that wider economic activity.

Golf Course Due to Open in First Half of 2027

The regional government expects the golf course to be completed in the first half of 2027. PS lawmakers say they will keep monitoring the project's costs and outcomes.

Investor Tender Closes This Friday, November 20

The public tender for the concession and land sale initially drew no interested investors, forcing the government to extend it. Officials then lowered both the price and the conditions attached to the deal.

The revised tender is now scheduled to close on 20 November, this Friday. The government says the winning bidders for the real estate and golf course operation will be known within a month. PS lawmakers argue that the lack of early private-sector interest is itself a sign of the project's weak financial and economic viability.

Source: madeira.rtp.pt